Question:

A business analyst has just facilitated a requirements-gathering session. The following week, the project manager started the process of capturing and documenting the project’s deliverables and developing a WBS. The business analyst and project manager are carrying out processes that belong to which of the following Knowledge Areas?

A Project Scope Management
Explaination

The business analyst and the project manager have carried out activities relating to the following processes: Collect Requirements, Define Scope, and Create WBS. These processes belong to the Project Requirements Management is not an official Knowledge Area.