Question:

A project manager considers the skills and capabilities needed to achieve planned outcomes of a project, including the type and quantities of material, equipment, and supplies. What activity is the project manager involved in?

A Estimating resource needs
Explaination

The project manager is carrying out activities associated with the Estimate Activity Resources process. Activities of this process include estimating team resources and the type and quantities of material, equipment, and supplies needed to carry out the project work.