A project manager discusses with the project sponsor for a weekly update. Company performance has been rocky, and the sponsor nervously asks what the chances are of the project upcoming to an accomplished closure. To date, the project has been on track and is nearing the end of Execution. How should the project manager react?

A The likelihood of successful completion is high.
Explaination

The chances for successful completion during the Executing phase are medium to high. Since the project is nearing the end of execution and is currently on track, the likelihood of success is high.