Question:

A project manager facilitates the voting process for decision-makers who have united to review a major outcome that has been completed. The intent of the discussion is to vote on whether to approve and accept the deliverable. What main input will the committee need to reference to elect?

A Verified deliverables
Explaination

The project manager is performing the Validate Scope process in this scenario, where a key output is the accepted deliverables. To accept deliverables, the committee would need to confirm that they have been verified through quality control activities. Verified deliverables are an input of the process.