A project manager has facilitated the separation of work packages into activities. She next carries the team through several exercises to sequence the activities and determine what and how many resources will be needed to perform the work. Select the action that she is likely to do next?

A Estimate how long each activity will take
Explaination

The project manager has performed the Define Activities, Sequence Activities, and Estimate Activity Resources processes. Next, she is likely to perform the Estimate Activity Durations process to determine how long each activity will take.