Question:

A project manager has just closed out a procurement, which yielded the final deliverable of the project. What action the project manager is likely to do next?

A Perform administrative closure
explanation

Since the scenario outlined that the final deliverable of the project was completed, it implies that closing activities would follow. Administrative closure, which occurs as part of activities such as ensuring that exit criteria have been met and contractual agreements were properly closed out, measuring stakeholder satisfaction, and ensuring that ongoing operational or sustainment activities are transferred to operations.

Related Information

Comments

edenegayle

4 years ago

I’m not sure how this app is accurate, simple & effective along with FREE? But I’m so grateful. Getting professional qualifications can be so expensive & daunting to tackle. This test taking, review-type app has been so extremely helpful. The structure of the app is so intuitive. It definitely helps with giving you an understanding of why something is wrong / right & making sure it sticks. Absolutely love it & I'm so grateful.

nikhildv

3 years ago

This app has been a great help, It gives perspective with the answers and that helps you prepare ... thanks for sharing it.

kerbs2CB

3 years ago

This app helped me pass my PMP today. The questions are not exactly as they are on the test but they help you with gaining the knowledge you need to pass the test! And it is free! I would recommend this to anyone studying for the PMP.

Leave a Reply

Your email address will not be published. Required fields are marked *

*