A project manager has just wrapped up a achieved project in an environment that implemented a streamlined hybrid approach to project delivery. Who wrote the project’s final report?

A Project manager
Explaination

The project manager is typically responsible for authoring the final report. The project’s final report contains a summary of what occurred on the project and may include information on scope, cost, schedule/burn down of work, risk, and quality outcomes.