Question:

A project manager has organized his project in a way that will allow for the planning of the project to happen during the early stage of the life cycle, with minimal changes thereafter. This approach is referred to which development life cycle?

A Predictive
Explaination

In a predictive life cycle, the project’s scope, time, and cost are determined during the early phases of the project, meaning that the majority of planning occurs up front. Changes are closely managed following a change control process.