A project manager is in the process of holding a kickoff discussion to signal that execution of the project work is about to start. She oversees the project baseline, communication cadence, and guidelines with the team, and she treats them to a pizza party to raise morale. Which of the following record serves as the project baseline?

A Project management plan
Explaination

The project management plan is a compilation of plans and baselines and is considered to represent the project baseline. Once work is executed, progress will be measured against this plan.