Question:

A project manager is operating a project working to create a fitness tracking device. He has just completed getting the project authorized and analyzing stakeholder needs and expectations. What activity is he likely to carry out next?

A Put together the project management plan
Explaination

The project manager has carried out the Develop Project Charter and Identify Stakeholders processes. He will likely begin to assemble the project management plan as a next step, by performing activities outlined within the Develop Project Management Plan process.