Question:

A project manager is operating a project working to generate a fitness tracking device. Using an adaptive approach to managing the schedule, the project manager discusses with the team to update and prepare stories for the upcoming iteration, accounting for any recent changes that may have happened. This is a case of:

A Backlog refinement
Explaination

Preparing stories for the next iteration refers to backlog refinement or backlog grooming. The intent is to refine stories sufficiently so that the team understands what work must be accomplished.