Question:

A project manager is operating with a risk manager to prioritize individual project risks. What project management process is connected with this activity?

A Perform Qualitative Risk Analysis
Explaination

The purpose of the Perform Qualitative Risk C. The purpose of the Perform Qualitative Risk Analysis process is to prioritize individual project risks for further analysis or action by assessing their probability of occurrence and impact as well as other characteristics.