A project manager is performing activities related to monitoring and controlling the scope of the project. What main information can they practice in conjunction with the plan to help them implement?  

A Work performance data     
Explaination

The project manager will need to measure the scope completed against the scope planned. To do this, they will need work performance data, a key input of the Control Scope process. Variance and trend analyses are tools and techniques of the process, not inputs.