header bg

Scan QR code or get instant email to install app

Question:

A project manager is performing activities related to monitoring and controlling the scope of the project. What main information can they practice in conjunction with the plan to help them implement?  

A Work performance data     
explanation

The project manager will need to measure the scope completed against the scope planned. To do this, they will need work performance data, a key input of the Control Scope process. Variance and trend analyses are tools and techniques of the process, not inputs.

Related Information

Comments

Abhishek Pandya

2 years ago

Definitely would recommend. I would use it as a tool to study for PMP. Helped me pass on the 1st attemp

Ahmed Mohamed AbdulKadir

2 years ago

Good Application for Project management

Diego Dutra

2 years ago

I love this app so far. Incredible app

Leave a Reply

Your email address will not be published. Required fields are marked *

*