Question:

A project manager of a large manufacturing company is working on a new system that will decrease the bolt manufacturing process by 30 seconds, saving the company 2 percent in annual operating costs. This project will touch all departments and involve senior leadership. The project manager understands stakeholder engagement will be critical to success and sets up a brainstorming session with the sponsor to build the initial list of stakeholders. She then engages those individuals to further capture other stakeholders that will need to be involved and collect any information available about them in order to conduct stakeholder analysis. Where will the project manager record this information?

A Stakeholder register
Explaination

The stakeholder register is the project artifact where information about identified stakeholders is captured. The stakeholder register typically includes identification information, assessment information, and stakeholder classification.