Question:

A project manager operates with the project team to recognize lessons learned. The information recorded will then be archived and summarized within the project’s final report. What activity is the project team engaged in?

A Administrative closure
Explaination

The project team is performing administrative closure activities associated with the Close Project or Phase process. While information captured will be added to the lessons learned register, administrative closure is a broader choice that captures additional activities noted in the question, such as archiving information and creating the final report.