Question:

A project manager operates within a department that has a PMO. The primary aim of the PMO organization is to make sure that the department receives the support needed to deliver successful project results, as well as remain compliant with published project governance requirements. What is the type of PMO named?

A Controlling
Explaination

There are three types of PMOs: supportive, controlling, and directive. Controlling PMOs are concerned with providing project teams with support, such as through published resources and templates, and ensuring compliance with published project management and governance frameworks.