Question:

A project manager operating within an Agile PMO is using a new approved contractor to fast-track the implementation of cloud-based solutions for her project. As part of reviewing the procurement activities for the project, she conducts a structured review of the work performed by the contractor. Which tool and technique does this question reflect?

A Inspection
Explaination

Inspection may involve a simple or physical review of the work performed by a contractor. It is structured in nature and is meant to ensure that a mutual understanding exists of the work in progress.