Question:

A risk manager united with the project manager to discuss the progress of the project. The risk manager expressed concerns about feedback received regarding the low likelihood that the team would gain their go-live date successfully. What activity is the project manager likely to do next?  

A Submit a change request in the form of preventive action.     
Explaination

Since an issue has not occurred as of yet, the project manager is likely to take preventive actions. Preventive actions are submitted through a change request, which is then evaluated and dispositioned through the project’s change control board.