Question:

A risk manager united with the project manager to discuss the progress of the project. The risk manager expressed concerns about feedback received regarding the low likelihood that the team would gain their go-live date successfully. What activity is the project manager likely to do next?  

A Submit a change request in the form of preventive action.     
explanation

Since an issue has not occurred as of yet, the project manager is likely to take preventive actions. Preventive actions are submitted through a change request, which is then evaluated and dispositioned through the project’s change control board.

Related Information

Comments

edenegayle

4 years ago

I’m not sure how this app is accurate, simple & effective along with FREE? But I’m so grateful. Getting professional qualifications can be so expensive & daunting to tackle. This test taking, review-type app has been so extremely helpful. The structure of the app is so intuitive. It definitely helps with giving you an understanding of why something is wrong / right & making sure it sticks. Absolutely love it & I'm so grateful.

nikhildv

3 years ago

This app has been a great help, It gives perspective with the answers and that helps you prepare ... thanks for sharing it.

kerbs2CB

3 years ago

This app helped me pass my PMP today. The questions are not exactly as they are on the test but they help you with gaining the knowledge you need to pass the test! And it is free! I would recommend this to anyone studying for the PMP.

Leave a Reply

Your email address will not be published. Required fields are marked *

*