Question:

A small sample of your project’s critical path is given in the following table. Assuming each activity must complete before the next activity can start, which of the following options is inaccurate?

A To complete the chart and determine the remaining dates for activity 4, you have to perform a backward pass.
Explaination

To calculate the early start and early finish for activity 4, you need to perform a forward pass. This is done by adding the duration of activity 4 to the early finish date of activity 3.