Question:

A small sample of your project’s critical path is represented in the following table. Assuming each activity must complete before the next activity can begin, select the late start and late finish date for activity 3?

image
A Late start is 5/29, and late finish is 6/4.
explanation

Late finish is calculated by subtracting the duration of the last activity (activity 4) from its start date. Since it is one day, that means the late finish is 6/4. Late start is 7 days prior to 6/4, which is 5/29.

Related Information

Comments

edenegayle

4 years ago

I’m not sure how this app is accurate, simple & effective along with FREE? But I’m so grateful. Getting professional qualifications can be so expensive & daunting to tackle. This test taking, review-type app has been so extremely helpful. The structure of the app is so intuitive. It definitely helps with giving you an understanding of why something is wrong / right & making sure it sticks. Absolutely love it & I'm so grateful.

nikhildv

3 years ago

This app has been a great help, It gives perspective with the answers and that helps you prepare ... thanks for sharing it.

kerbs2CB

3 years ago

This app helped me pass my PMP today. The questions are not exactly as they are on the test but they help you with gaining the knowledge you need to pass the test! And it is free! I would recommend this to anyone studying for the PMP.

Leave a Reply

Your email address will not be published. Required fields are marked *

*