Question:

A small sample of your project’s critical path is represented in the following table. Assuming each activity must complete before the next activity can begin, select the late start and late finish date for activity 3?

A Late start is 5/29, and late finish is 6/4.
Explaination

Late finish is calculated by subtracting the duration of the last activity (activity 4) from its start date. Since it is one day, that means the late finish is 6/4. Late start is 7 days prior to 6/4, which is 5/29.