header bg

Question:

All of the following are correct except which one?

A The team members coming from the consulting company are accounted for in the Plan Procurement Management process and Plan Resource Management process, not this process.
Explaination

The Acquire Resources process is concerned with all resources for the project, both existing staff members and consultants or external staff. The procurement processes are used to obtain the staff members, and the Acquire Resources process involves attaining and assigning resources.