All of the following are correct regarding project life cycles except:

A Toward the end of the project, stakeholders have the greatest chance of influencing a project.
Explaination

Stakeholders have the greatest chance of influence over the project and the characteristics of the product, service, or results of the project in the early phases of the project, not the end. All other statements are true.