Question:

All of the following are correct regarding the organizational process assets updates output of the Manage Communications process except which one?

A Feedback from stakeholders is part of this output and can improve performance on future projects, but it is too late to incorporate the feedback on the current project.
Explaination

All the options are part of the organizational process assets updates output of this process. Feedback from stakeholders can be used on the current project as well as future projects.