Question:

All of the following are correct regarding the Perform Integrated Change Control process except for which one?

A This process is carried out as part of executing the project work.
explanation

The Perform Integrated Change Control process is carried out as part of monitoring and controlling the activities, which occurs in conjunction with execution activities but is not itself considered part of the Executing process group.