Question:

All of the following comments are true regarding the information in this question EXCEPT:

A The technique Carrie used can also be used to estimate project duration because of the amount of information available about the details of the project.      
explanation

Carrie used the analogous estimating technique, which is a form of expert judgment. It is a tool and technique of the Estimate Activity Durations process. Analogous estimating bases estimates on previous activities that are similar in fact, and they require the person estimating them to have expertise in the activity. Analogous estimating techniques are typically used to estimate project duration when there is a limited amount of information about the project.

Related Information

Comments

edenegayle

4 years ago

I’m not sure how this app is accurate, simple & effective along with FREE? But I’m so grateful. Getting professional qualifications can be so expensive & daunting to tackle. This test taking, review-type app has been so extremely helpful. The structure of the app is so intuitive. It definitely helps with giving you an understanding of why something is wrong / right & making sure it sticks. Absolutely love it & I'm so grateful.

nikhildv

3 years ago

This app has been a great help, It gives perspective with the answers and that helps you prepare ... thanks for sharing it.

kerbs2CB

3 years ago

This app helped me pass my PMP today. The questions are not exactly as they are on the test but they help you with gaining the knowledge you need to pass the test! And it is free! I would recommend this to anyone studying for the PMP.

Leave a Reply

Your email address will not be published. Required fields are marked *

*