All of the following statements about the arrow diagramming method (ADM) are correct except which one?

A ADM allows for multiple types of dependencies, including finish-to-start, start-to-finish, start-to-start, and finish-to-finish.
Explaination

ADM only uses the finish-to-start dependency. Precedence diagramming method (PDM), on the other hand, uses all dependency types.