header bg

Scan QR code or get instant email to install app

Question:

As a result of a face-to-face conservation you recently had, you have addressed an issue and have come away with an update to the issue log, change requests, project management plan updates, and project documents updates, and you have submitted a change request. You know all of the following are accurate regarding this except which one?

A This describes the Manage Communications process.
explanation

This question lists all the outputs of the Manage Stakeholder Engagement process. The issue log is used more like an action item log in this process.

Related Information

Comments

Nur Aishah Hussin

1 year ago

grateful for this app. thanks all!

Collins Yaw Mensah

1 year ago

The best pmp prep app to pass your pmp exams

gonzalezfrank

1 year ago

So far my favorite app that I have used to study

Leave a Reply

Your email address will not be published. Required fields are marked *

*