Question:

As a result of a face-to-face conservation you recently had, you have addressed an issue and have come away with an update to the issue log, change requests, project management plan updates, and project documents updates, and you have submitted a change request. You know all of the following are accurate regarding this except which one?

A This describes the Manage Communications process.
explanation

This question lists all the outputs of the Manage Stakeholder Engagement process. The issue log is used more like an action item log in this process.