Question:

As part of project integration management activities, a project manager reports on value gained to date against the plan. What does the project manager hope to achieve by carrying out this activity?

A Appraise stakeholders of the project’s progress against the benefits management plan
Explaination

The benefits management plan outlines the target benefits of the project and is used to measure both the tangible and intangible benefits. As part of project integration management activities, project managers should report progress against this plan to project stakeholders.