Question:

As project manager, what action should you perform?  

A Inform the customer that you’ve discovered this condition and tell them you’ll research it further to determine its impacts. 
explanation

Honesty and truthful reporting are required of PMP credential holders. In this situation, you would inform the customer of everything you know regarding the problem and work to find alternative solutions.

Related Information

Comments

Юрий Фамилия

2 years ago

отличное приложение, помогает готовиться, спасибо разработчикам!!!

Marc Lum Lock

2 years ago

Thus far it has been very helpful. The various situations really get you to think as a PM and consider the tricky ones as well. I do have a concern, though. Seeing that the edition for the exam has recently changed to the 7th edition, would the app also be updated to fit thosd new domains etc? I'd like to ensure I'm following the appropriate material

Christian-Marc G AKA_Sounouvi

2 years ago

Aide pour apprendre et se préparer à l'examen... Let's hope nothing will make me change my statement Merci

Leave a Reply

Your email address will not be published. Required fields are marked *

*