Question:

Carina is a principal project manager of You’ve Got Dogs, a specialty company that produces custom dog apparel and toys. She has just achieved approval of the project management schedule and is about to publish it to the project team. At this point in the project life cycle, costs are likely to be which of the following?

A Low
Explaination

Carina is concluding major activities associated with the Planning process group and is getting ready to enter into Executing. At this point in the project life cycle, costs are typically low.