Question:

Carina is a principal project manager of You’ve Got Dogs, a specialty company that produces custom dog apparel and toys. She has just achieved approval of the project management schedule and is about to publish it to the project team. At this point in the project life cycle, costs are likely to be which of the following?

A Low
explanation

Carina is concluding major activities associated with the Planning process group and is getting ready to enter into Executing. At this point in the project life cycle, costs are typically low.

Related Information

Comments

edenegayle

4 years ago

I’m not sure how this app is accurate, simple & effective along with FREE? But I’m so grateful. Getting professional qualifications can be so expensive & daunting to tackle. This test taking, review-type app has been so extremely helpful. The structure of the app is so intuitive. It definitely helps with giving you an understanding of why something is wrong / right & making sure it sticks. Absolutely love it & I'm so grateful.

nikhildv

4 years ago

This app has been a great help, It gives perspective with the answers and that helps you prepare ... thanks for sharing it.

kerbs2CB

4 years ago

This app helped me pass my PMP today. The questions are not exactly as they are on the test but they help you with gaining the knowledge you need to pass the test! And it is free! I would recommend this to anyone studying for the PMP.

Leave a Reply

Your email address will not be published. Required fields are marked *

*