Question:

Carina is a principal project manager of You’ve Got Dogs, a specialty company that produces custom dog apparel and toys. As part of her latest project, she interviews experienced subject-matter professionals to better understand what risks exist within the project. Where will she save her findings?

A Risk register
Explaination

Carina will update risks identified and information about the risks within the risk register. While project documents are technically a correct answer (since the risk register is a project document), the risk register is more specific and therefore a better choice. Her findings may also find their way into the risk report, although, again, that is a secondary choice.