Question:

Choose the best statement that describes overall project risk?

A The effect of uncertainty on the project as a whole, arising from all sources of uncertainty.
Explaination

According to the PMBOKĀ® Guide, there are two levels of risk: individual project risk and overall project risk. An overall project risk is the effect of uncertainty on the project as a whole, arising from all sources of uncertainty.