Question:

Contract phases are closely associated to the Project Procurement Management Knowledge Area processes. All of the following are correct except for which one?

A The requisition stage, where responses to procurement documents are reviewed, is related to the Conduct Procurements process.
Explaination

The requisition stage is where the procurement documents are prepared (not the responses to them) and is associated with the Plan Procurement Management process. The two outputs that become inputs are procurement documentation and source selection criteria.