Question:

During the execution phase of a biotech project, a new problem has surfaced. What is one of the first things that the project manager should take?

A Note the issue within an issue log
Explaination

The best choice is to note the issue within the issue log. The reason for this is that an owner can then be assigned to the issue, and a target resolution date set. This allows for more structured and documented resolution. The issue log is also something that will be archived at a later date within the project files.