Question:

Following the parametric estimating technique, how many hours will it take the team to run the cable?

A 12
Explaination

Parametric estimating is a quantitatively based estimating method that multiplies the quantity of work by the rate or uses an algorithm in conjunction with historical data to determine cost, budget, or duration estimates. Based on this definition, take 1,320 and divide by 110 to get 12.