Question:

How are his actions likely to be judged by the contracting organization?

A As a violation of intellectual property
explanation

Given that the project manager contributed to the handbook while under assignment by the contracting organization and was just one of multiple contributors, it is likely that his actions would be viewed as a violation of the organization’s policies on intellectual property. This would be verified by reviewing the project manager’s contractual agreement.