Question:
To determine performance against the budget, you must first calculate variance at completion. To calculate variance at completion, subtract the estimate at completion from the budget at completion (BAC – EAC): $550,000 – $525,000 = $25,000. A positive VAC means that the project is performing under the planned costs.