Question:

How will Marysil reflect this within the plan?  

A By adding a two-day lag between the two activities 
Explaination

Marysil will need to add a lag between the activities. A lag occurs when time must elapse between two activities, where the delay is added to the successor activity. A lead, on the other hand, speeds up the successor activity.