header bg

Scan QR code or get instant email to install app

Question:

If Activity A has an early start of 10, an early complete of 16, and a late start of 12, what is the total float of the activity?

A 2
explanation

Total float refers to the amount of time you can delay the earliest start of an activity without delaying the earliest start of an activity without delaying the ending of the project. To calculate total float, subtract either the early start from the late start or the early finish from the late finish (both give you the same answer).

Related Information

Comments

edenegayle

4 years ago

I’m not sure how this app is accurate, simple & effective along with FREE? But I’m so grateful. Getting professional qualifications can be so expensive & daunting to tackle. This test taking, review-type app has been so extremely helpful. The structure of the app is so intuitive. It definitely helps with giving you an understanding of why something is wrong / right & making sure it sticks. Absolutely love it & I'm so grateful.

nikhildv

3 years ago

This app has been a great help, It gives perspective with the answers and that helps you prepare ... thanks for sharing it.

kerbs2CB

3 years ago

This app helped me pass my PMP today. The questions are not exactly as they are on the test but they help you with gaining the knowledge you need to pass the test! And it is free! I would recommend this to anyone studying for the PMP.

Leave a Reply

Your email address will not be published. Required fields are marked *

*