Question:

If earned value = 500, planned value = 700, and actual costs = 450, Calculate the cost variance?

A 50
Explaination

To calculate schedule variance, subtract planned value from earned value (CV = EV – AC): $500 – $450 = $50. A positive cost variance means that the project is under budget.