Question:

Jane, who is the project manager, has a question about the Research activity’s progress and is interested in knowing why it emerges to have fallen behind. According to the given RACI chart, who is to perform the work of this activity?

image
A Alfred
explanation

RACI stands for responsible, accountable, consult, and inform. The chart identifies Alfred as being responsible for the Research activity, making him the correct answer. Responsible indicates who will be performing the work.