Question:

Marysia is an enterprise project manager for Cups on Fire. To date, she has identified risks, analyzed them, and developed a risk responses system for her project. Now, she and the team are executing the work and reacting to risk triggers. Select the name of the project management artifact will they need?

A Risk register
Explaination

The risk register contains the list of identified risks and all information documented about them, including the risk response plans. As risk triggers occur, they will need to refer to the risk register for information about the risk response plans.