Question:

Marysil, an enterprise project manager for Cups on Fire, kicked off activities to build the schedule. To date, she has created the schedule management plan and led the team through a separation of work packages into activities. Now, she and the team are sequencing activities. She plans on performing a visual using a network diagram during the next discussion. What network diagramming remedy is she most likely to practice?

A Precedence diagramming method
Explaination

Precedence diagramming method (PDM) is the most frequently used diagramming method. PDM uses boxes to represent activities and connects the activities with arrows showing the dependencies between them. PDM is also known as activity on node (AON).