header bg

Scan QR code or get instant email to install app

Question:

Marysil is an enterprise project manager for Cups on Fire. To date, she has identified risks, analyzed them, and developed risk responses for her project. What activity is she likely to perform next?

A Implement risk responses
explanation

Based on the activities Marysil has already carried out, the next logical step would be to begin implementing the risk responses based on plans documented in the risk register. While some risk responses are implemented when risk triggers occur, others are implemented immediately to avoid or exploit a risk.

Related Information

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *

*