Question:

Plan Schedule Management, Estimate Activity Durations, and Control Schedule are processes that belong to what project management Knowledge Area?

A Project Schedule Management
Explaination

Plan Schedule Management, Estimate Activity Durations, and Control Schedule are processes that belong to the Project Schedule Management Knowledge Area. Other processes belonging to this Knowledge Area include Define Activities, Sequence Activities, and Develop Schedule.