Question:

Premature closure of a project phase that is operating using an Adaptive approach is likely to experience greater failure because of sunk costs versus a project managed practicing a Predictive approach.

A This is a false statement.
Explaination

This is a false statement. Projects using an Adaptive approach prioritize work based on the highest business value items first. This reduces the failure of premature closure due to sunk costs because early benefits realization occurs.