Question:

Ron meets with Bob, the appointed project manager, to ask when the other project team members will be assigned to the project he is scheduled for. Since team assignments have not been given yet, how does Ron know he will be appointed to the project?

A Ron was pre-assigned and listed in the project charter.
explanation

The question is referring to pre-assignments, which can be negotiated within the contract, can be included in the project charter, or can be a result of a project that revolves around a staff member’s expertise. Pre-assignments is used as a tool and technique of the Acquire Team process.