Question:
Ronaldo has just participated in the company as a project manager and is taking over an active project that is in the process of developing the schedule. The previous project manager did a good job of remaining project management documents up-to-date. Which project management document can Ronaldo reference that will outline the methodology and tools the team is using to display schedule network analysis?
A
Schedule management plan
Explaination
The schedule management plan documents the method and approach for developing, managing, and controlling the project schedule.