Question:

Sally is a project manager who works at Galactic Kidz. While managing the execution of the project team’s work, she notices that two critical activities are delayed and decides to speak to the project sponsor. What action are Sally and the project sponsor likely to take?  

A Corrective action     
Explaination

The scenario notes that two critical activities are already delayed, meaning that an issue has been identified and must be addressed. While updates to the plan are likely, they will be the result of corrective action taken.