Question:

Select the likely reason for this pushback from the team?

A They are accustomed to using an adaptive approach to managing projects.
explanation

Albert is attempting to manage the project using a predictive approach, which aims to identify the majority of requirements early on in the project’s life cycle. A technology startup environment, coupled with a high-uncertainty project, is likely to lean toward an adaptive approach to managing projects.